This guide will assist you in setting up half day rest day on Saturday.


To setup half day rest day, go to Tools > General Maintenance > Calendar.


Click on the pencil icon to edit the calendar.



Select the Advance option, copy the settings as shown below & click on Apply.



If there are any date conflicts with holiday. You can choose whether you want that day to be a Rest day or Holiday. After that, click on Save.



Once done, click on Save at the top right corner to save the overall changes.


END OF GUIDE